Data Center compatibility

Description

A few customers are asking for DC compatibility. This issue will track our progress on it.

What we have

We are cluster-compatible, meaning we complied to the previous requirements of Atlassian regarding datacenters. We use shared, serializable caches as recommended, we use pagination for large sets of data, etc.

What we are missing before applying to Atlassian's DC certification

Nothing, we are Data Center-ready.

What this issue doesn't include

  • The PSEA module is not included, it is under test and will be published in a few weeks,

  • The Jira module is not included, it requires more work and will be published when ready (ETA: September),

  • The TC module (Test & Compliance) is not included, it will not undergo a Data Center approval.

Environment

None

Observations

None
Resolved

Assignee

Unassigned

Reporter

Adrien Ragot (Old account)

Labels

None

Participants

None

Components

Fix versions

Priority

Matter of months